KYOCERA TCL Solar Completes 28MW Solar Power Plant in Miyagi Prefecture, Japan
Kyocera Corporation and Tokyo Century Corporation announced that Kyocera TCL Solar LLC has completed construction of a 28 megawatt (MW) utility-scale solar power plant in the town of Taiwa, Kurokawa District, Miyagi Prefecture, Japan. The company has developed this 28MW solar power plant in collaboration with Tokyo-based Tsuboi Corporation and started operations in late June 2018.
This is the company’s first solar power plant in Miyagi Prefecture and its second largest solar power plant following the 29.2MW solar power plant in Tottori Prefecture. 103,950 Kyocera solar modules will generate an estimated 33,000 megawatt hours (MWh) per year — enough electricity to power approximately 11,100 average households and capable of providing power to almost all the local households in the town of Taiwa which is adjacent to Sendai City, the heart of the Tohoku region. With more companies entering Miyagi Prefecture’s largest industrial park in this area, it is experiencing urbanization and population growth. The company hopes its solar power plant will be a local symbol of supporting people’s lives and developing the local community while coexisting with the region’s rich nature.
Kyocera TCL Solar has constructed solar power plants in 67 sites across Japan including this 28MW plant, with approximately 258.1 MW of total output since the company was established in August 2012. Kyocera TCL Solar, Kyocera and Tokyo Century remain committed to promoting renewable energy as well as contributing to environmental protection and the creation of a sustainable society through their solar energy business.
Project Overview
Location | Taiwa Town, Kurokawa District, Miyagi Prefecture, Japan |
Operation | Kyocera TCL Solar LLC |
Joint planner/land proprietor | Tsuboi Corporation |
Design, construction and maintenance | Kyocera Solar Corporation, Tsuboi Corporation |
Maximum output | Approx. 28MW |
Solar modules | 270-watt Kyocera modules: 92,070 280-watt Kyocera modules: 11,880 Total: 103,950 |
Expected annual power generation | Approx. 33,000 MWh (enough electricity to power approximately 11,100 typical households) |
Electric power sales destination | Tohoku Electric Power Co., Inc. |
Start of operation | June 21, 2018 |
Company Overview
Company name | Kyocera TCL Solar LLC |
Location | Chiyoda-ku, Tokyo, Japan |
Shareholders | Tokyo Century Corporation (81%) Kyocera Corporation (19%) |
Established | August 2012 |